      SCOPE DESCRIPTIONS

       

      Supply pipe & fitting material, Erection piping work & Testing  about 1000 DB.

       

       

       

       

      PROJECT / OWNER

       

       

      Changing Piping for Reactor R-300

       

      Owner : Thai GCI resitop , Ltd. 

      WORK EXECUTION 2008



       
      DURING WORK TIME

       

       

       As of January 2008

      DURING WORK TIME

       

       

       As of February 2008

      PROJECT / OWNER

       

       

      FABRICATION OF SAMPLING COOLER  3 ITEM

       

      Owner : Global Engineering Solution Co., ltd.

      SCOPE DESCRIPTIONS

       

      Supply material, Fabrication, painting & Inspection work.

       

       

       

       

      SCOPE DESCRIPTIONS

       

      Shop drawing, Supply material, Fabrication, Painting & Inspection work.

       

       

       

       

      DURING WORK TIME

       

       

       As of March 2008

      PROJECT / OWNER

       

       

      FABRICATION OF TANK  1 ITEM (SS400 Grade)

       

      Owner : Kessel (Thailand) Co., ltd.

      DURING WORK TIME

       

       

       As of April 2008

      PROJECT / OWNER

       

       

      Piping arrangement  drawing & Isometric  drawing 

       

      Owner : Sutee Group Co.,ltd.

      SCOPE DESCRIPTIONS

       

      Site survey & Arrangement of  piping arrangement drawing / Isometric drawing.  

       

       

       

       

      DURING WORK TIME

       

       

       As of May 2008

      PROJECT / OWNER

       

       

      Arrangement  of  Plot plan drawing 

       

      Owner : Sutee Group Co.,ltd.

      SCOPE DESCRIPTIONS

       

      Site survey & Arrangement of  plot plan drawing 

       

       

       

       

      DURING WORK TIME

       

       

       As of June 2008

      PROJECT / OWNER

       

       

      Changing Piping for Reactor R-300

       

      Owner : Thai GCI resitop , Ltd. 

      SCOPE DESCRIPTIONS

       

      Supply pipe & fitting material, Erection piping work & Testing.  

       

       

       

       

      DURING WORK TIME

       

       

       As of September - October 2008

      PROJECT / OWNER

       

       

      Changing Piping for Reactor R-50,R100 & R200

       

      Owner : Thai GCI resitop , Ltd. 

      SCOPE DESCRIPTIONS

       

      Supply pipe & fitting material, Erection piping work & Testing  about 2300 DB.

       

       

       

      DURING WORK TIME

       

       

       As of October - November 2008

      PROJECT / OWNER

       

       

      BIO Piping project

       

      Owner : Global Engineering Solution Co., ltd.

      SCOPE DESCRIPTIONS

       

      Civil engineering, Piping / Iso metric drawing, Footing calculation and pipe support foundation construction.